send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
50 persons are employed to complete a work in 30 days working 12 hours each day. Due to some reason, they work for only 10 hours for the first 15 days. After this, 10 persons leave the work and rest continues the work as before. How many more days are needed to complete the work than the actually estimated time?
11 1/4 days
12 2/3 days
10 1/2 days
12 days
Explanation: 50 men work for 10 hours for first 15 days. Let they complete x work So 50 * 12 * 30 * x = 50 * 10 * 15 * 1 Solve, x = 5/12 So remaining work = 7/12 which is to be done by 40 men (as 10 men leave after 15 days). Let they complete work in y days. So 50 * 12 * 30 * 7/12 = 40 * 10 * y * 1 So y = 105/4 days So extra days = 105/4 – 15 = 45/4 days = 11 1/4 days