send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Kavita can complete a piece of work alone in 12 hours, while Komal can complete the same work alone in 18 hours. Kavita
works alone for the first 4 hours and leaves. After that, Komal comes and completes the remaining work by herself. How much
time did Komal take to finish the remaining work?
15 hours
10 hours
16 hours
12 hours
- Kavita's work rate is 1/12 of the work per hour.
- Komal's work rate is 1/18 of the work per hour.
- Kavita works alone for 4 hours, completing 412=13 of the work.
- Thus, 23 of the work is still left.
- Komal needs to complete the remaining 23 of the work.
- Time taken by Komal to finish this is 2/31/18=12 hours.
- Correct Answer: Komal takes 12 hours to finish the remaining work.