send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A work can be completed by 20 men in 50 days. 30 more men join them after 10 days of work. How many days will be saved in
completion of the work?
18 days
20 days
24 days
28 days
- Initially, 20 men can finish the work in 50 days.
- Hence, total work units = 20 men * 50 days = 1000 man-days.
- For the first 10 days, these 20 men complete 20 men * 10 days = 200 man-days of work.
- Remaining work is 1000 - 200 = 800 man-days.
- After 10 days, 30 more men join. So, total men now = 20 + 30 = 50 men.
- 50 men complete the remaining 800 man-days of work.
- Days needed to complete 800 man-days = 800 man-days / 50 men = 16 days.
- Total days = 10 days + 16 days = 26 days.
- Originally, the project was planned for 50 days.
- Days saved = 50 - 26 = 24 days.
- Option:3 - 24 days is the correct answer.