send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Radha can complete a piece of work in 3 days, while Raji can complete the same work in 2 days. Both of them complete this
work by working together and get Rs150 as total payment for the work done. What is the share of Radha out of the above
payment?
Rs70
Rs40
Rs30
Rs60
- Radha can complete the work in 3 days, so she does 1/3 of the work in a day.
- Raji can complete the work in 2 days, so she does 1/2 of the work in a day.
- Together in one day, they complete: 1/3 + 1/2 = 2/6 + 3/6 = 5/6 of the work.
- Therefore, they complete the work together in 6/5 days.
- Radha's contribution to the work is (1/3) / (5/6) = 2/5.
- Raji's contribution is (1/2) / (5/6) = 3/5.
- Total payment is Rs150.
- Radha's share is 2/5 of Rs150 = Rs60.
- Raji's share is 3/5 of Rs150 = Rs90.
- Correct Answer: Rs60
.