send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
P can do a piece of the work in 18 days and Q can do same work in 36 days. How long will they take (in days), if they work
together, to complete the above mentioned work?
24
12
20
10
- P can complete the work in 18 days. This means P does 1/18 of the work each day.
- Q can complete the work in 36 days. Thus, Q does 1/36 of the work daily.
- Together, their combined work per day is:
- (1/18) + (1/36) = (2/36) + (1/36) = 3/36 = 1/12 of the work.
- Hence, both P and Q together take 12 days to complete the work.
Option 2: 12
- Option 1: 24 days - Too long, as they work together.
- Option 3: 20 days - Also too long for joint efforts.
- Option 4: 10 days - Slightly short; overestimates their speed.