send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A does half as much works as B in three-fourths of the time. If together they take 18 days to complete a work, how much time shall B take to do it?
30 days
35 days
40 days
none of these
Let b cab do 6 unit in 1 day
So a will do 3 unit in 3/4 th day . So 4 unit in full day.
So ratio of efficiency is 4 :6 or 2:3
So b will take 18 / (3/5) = 30 day
Hence, option 1 is the correct answer.