send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Jeni can do a job in 30 days, Nove in 45 days and Joel in 60 days. If Jeni is helped by Nove and Joel every 3rd day, how long will it take for them to complete the job?
21 5/6
8
9 3/4
10
Solution: Jeni 30…………………………..6 N 45 LCM180……….4 Joel 60 …………………………..3 1st two days =6*2=12unit work completed. 3rd day (6+4+3)= 13unit For 3 days 12+13=25unit completed 3*7=25*7 21=175 Remaining 5 unit done by Jeni Then 5/6work Then total 21 5/6days.