send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
12 labours can complete a work in 18 days. Six days after they started working, 4 labours joined them. How many days will all of them take to finish the remaining work ?
9 days
10 days
12 days
15 days
(12 * 18) labours can complete the work in 1 day. 1 labour's 1 days work = 1/216 12 labours 6 days work = (1/18)*6 = 1/3 Remaining work = 1 - (1/3) = 2/3 16 labours 1 days work = 16/216 = 2/27 2/27 work is done by them in 1 day. 2/3 work is done by them in (27/2)*(2/3) = 9 days.