send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
30 men take 25 days to dig a pond. If the pond would have been dug in 15 days, then what is the number of men to be employed?
45
60
50
57
none of these
- 30 men dig a pond in 25 days. The work can be represented as the product of men and days.
- This means: 30 men×25 days=750 man-days.
- The same pond needs to be dug in 15 days.
- To find the number of men needed, divide the total man-days by 15 days.
- Calculation: 750 man-days÷15 days=50 men.
- Option 3, 50 is correct.