send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A,B and C individually can do a certain piece of work in 35,42 and 24 days resp. They started working together but after ‘x’ days A and C left the job and the remaining work is completed by B with 25% more efficiency. If the whole work is completed in 114/5 days then find the value of x.
7
6
5
3
Total work (LCM of 35, 42 and 24) = 840 units Amount of work done by A,B and C = 24 , 20 and 35 units Amount of work done by A, B and C together in ‘x’ days = (24+20+35)*x = 79x units Amount of work done by B alone in one day after increased efficiency = 20*1.25 = 25 units Amount of work done by B alone in {(114/5) – x} days with increased efficiency = {(114/5) – 5} * 25 = (570 – 25x) units 79x + 570 – 25x = 840 => x = 5