send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A contractor takes a road construction project to finish it in 40 days and for that he engaged 200 men. After 30 days he employed 100 more men in this project, then the work finished on time. Find if the 100 more men would not worked then how many more days required to finish the work ?
8 days
10 days
12 days
5 days
Solution: 100 * 10 days = 1000 Now 1000/200 = 5 days (Initial total no. of men engaged in the project) Hence ,5 more days required to finish the work if 100 more men would not joined .