send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A contract is to be completed in 56 days and 104 men were set to work each working 8 hours a day. After 30 days, 2/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time, each man now working 9 hours day?
60
56
70
42
Persons worked (M1) = 104 Number of hours each person worked per day (H1) = 8 Number of days they worked (D1) = 30 Work completed (W1)= 2/5 Remaining days (D2)= 56 - 30 = 26 Remaining Work to be completed (W2)= 1 - 2/5 = 3/5 Let the total number of persons who do the remaining work (M2) = x Number of hours each person needs to be work per day (H2) = 9
M1D1H1W1 = M2D2H2W2 ⇒ 104×30×8 (25) = x×26×9 (35)
⇒104×30×82 = x×26×93
⇒52×30×8 = x×26×3
⇒2×30×8 = 3x
⇒x = 2×10×8 =160
Number of additional persons required = 160 - 104 = 56
Hence, option 2 is the correct answer.