send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
If 140 men working 8 hours per day can complete a piece of work in 30 days, how many hours per day must 20 men work to complete the same job in 12 days?
7 hrs
8 hrs
9 hrs
6 hrs
Total number of man hours needed to complete the work is 140*8*30
So, for 20 men to complete the work in 12 days,
the number of hours they need to work each day = (140*8*30)/(20*12) = 140 hours
1 men need to work each day = 140/20 = 7 hrs.
Hence, option 1 is the correct answer.