send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
12 men can complete a painting work in 8 days. However, 16 women can complete the same painting work in 12 days. 8 men started painting the house. After 6 days of painting 2 men were replaced by 4 women. Now how many days will they take to complete the remaining painting'?
4
6
8
5
Correct option 2: 6
Given
12 men can complete a painting work in 8 days.
So, total work in term of Man's days = 96.
and One day work of a man = 1/96
Similarly,
16 women can complete the same painting work in 12 days.
One day work of a woman = 1/16x12=1/192
Now we compare one day work of a man with one day work of a Woman.
1/96 : 1/192
1.e. 2:1
=> 1 man = 2 Women.
Now, 8 men started painting the house. After 6 days of painting 2 men were replaced by 4 women.
8 men's 6 days work = 48 units
Remaining work = 96- 48 = 48 units.
After 6 days 2 Men replaced with 4 women.
Now we have 4 Men + 4 Women
=> 6 Men + 2 Men ( because 4 women are equal to 2 Men)
=> 8 Men
Now, time required to complete the pending work = .48/8= 6 days
By: santosh ProfileResourcesReport error