send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
'A' can complete a work in 15 days and 'B' can complete the same work in 20 days. Working together, in how many days will they
complete 70% of the same work?
7
6
5
8
- 'A' can complete the work in 15 days, so 'A' does 1/15 of the work in a day.
- 'B' can complete the work in 20 days, so 'B' does 1/20 of the work in a day.
- Together, 'A' and 'B' can do 115+120=4+360=760 of the work in a day.
- To find how long they take to do 70% of the work, set up the equation: 760×days=0.7.
- Solving for the days needed gives: days=0.7×607=6.
- Therefore, they need 6 days to complete 70% of the work.
Correct answer is: Option:2, 6
Report error
Access to prime resources