send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
The ratio of the efficiencies of A, B and C, to do a certain workis 7 : 3 : 5. Working together, they can complete the work in 21
days. A and C worked together for 15 days. The remaining work will be completed by B alone in:
54 days
45 days
60 days
63 days
- A, B, and C's efficiency ratio is 7:3:5.
- The total work is completed by A, B, and C together in 21 days.
- Calculating the collective efficiency:
- Total efficiency = 7 + 3 + 5 = 15 units per day.
- Total work = total efficiency × total days = 15 units/day × 21 days = 315 units.
- A and C together have an efficiency of 7 + 5 = 12 units per day.
- They work together for 15 days, completing 12 units/day × 15 days = 180 units.
- Remaining work = 315 units - 180 units = 135 units.
- B's efficiency is 3 units/day.
- Days needed for B to complete the remaining work = 135 units / 3 units/day = 45 days.
- Correct Answer: Option 2: 45 days