send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as
good a work man as C, then in what time will B alone do 40% of the same work?
12 days
15 days
18 days
10 days
- Given that A and B together can finish the work in 20 days:
- Combined work rate of A and B: 1/20 of the work per day.
- B and C together can finish it in 24 days:
- Combined work rate of B and C: 1/24 of the work per day.
- A is twice as efficient as C, implying:
- A = 2C in terms of working ability.
- To find B's work rate:
- Assume C's work rate as x. Then A's work rate is 2x.
- A + B = 1/20, hence 2x + B = 1/20.
- B + C = 1/24, hence B + x = 1/24.
- Solving these equations gives us B's work rate:
- Subtract the second from the first: (2x + B) - (B + x) = 1/20 - 1/24
- x = 1/120
- Substitute x = 1/120 into B + x = 1/24 to find B = 1/30.
- B's work rate is 1/30 of the work per day.
- To find time for B to do 40% of the work:
- 40% of work is 0.4 of the total work.
- Time = Work / Rate = 0.4 / (1/30) = 12 days.
Option:1 - 12 days is correct.