send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
A can do a piece of work in 30 days, B can do in 45 days and C can do same work alone in 60 days. If on the first day A worked alone and on the second day A and B worked together and on the third day A and C worked together. If they repeat the cycle as follows then in how many days total work can be completed?
21 Days
21 7/8 Days
21 5/6 Days
21 4/9 Days
Explanation : First day = 1/30 Second day = 1/30+1/45 Third day = 1/30+1/60 3 days work = 3/30+1/45+1/60 = 25/180 3*7 = 21 days work = 175/180 Now 1/36 work is left which can be completed by A alone 1/36*30 = 5/6 21+5/6 = 21 5/6 Days