send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
P can do 1/2 of a work in 10 days and Q can do 1/5 of the same work in 4 days. In how many days can both finish the work,
working together?
14 days
10 days
15 days
5 days
- Worker P can complete half of the work in 10 days. This means P can complete the full work in 20 days.
- Worker Q can complete one-fifth of the work in 4 days. This implies Q can complete the full work in 20 days.
- To find out how many days they can complete the work together, sum their work rates.
- P's work rate is 1/20 of the work per day. Q's work rate is also 1/20 of the work per day.
- Together, P and Q can do (1/20 + 1/20) = 1/10 of the work per day.
- Thus, they can complete the entire work in 10 days.
Option:2 - 10 days
.
By: santosh ProfileResourcesReport error