send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Five men working together can complete a work in 8 days. Om Prakash who can complete the same work independently in 24
days joined them after 4 days. Under the circumstances in how many days the work will be completed?
5
3
7
4
- Five men working together can finish the work in 8 days. This means their combined work rate is 1/8 of the work per day.
- In 4 days, these five men finish 4/8 or 1/2 of the work.
- There’s 1/2 of the work left after 4 days.
- Om Prakash, who can do the work alone in 24 days, has a work rate of 1/24 per day.
- When Om Prakash joins after 4 days, the new combined work rate is 1/8 + 1/24 = 1/6 of the work per day.
- To complete the remaining 1/2 work at the rate of 1/6 per day, it will take 3 days.
- Thus, the entire work is done in 4 days (initial) + 3 days (after Om Prakash joins) = 7 days.
- Correct Answer: Option 3 - 7