send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of
that work in 16 days working 6 hours a day?
25
15
20
9
To determine how many persons are needed, let's break down the problem:
- We are given that 18 persons working 8 hours/day can complete 3 units in 10 days.
- Let's calculate the total man-hours required for 3 units:
- 18 persons × 8 hours/day × 10 days = 1440 man-hours.
- Thus, 1440 man-hours for 3 units means 1 unit = 480 man-hours.
- For 5 units, we need 5 × 480 = 2400 man-hours.
- New scenario: Complete 5 units in 16 days, working 6 hours/day.
- Calculate the total available hours for each person: 16 days × 6 hours/day = 96 hours/person.
- Total persons required = Total man-hours needed / Total available hours per person = 2400 / 96 = 25.
- Correct answer: Option 1 - 25 persons
By: santosh ProfileResourcesReport error