send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
60 men can complete a work in 40 days. They start work together but after every 10 day, 5 men leave the work. In how many
days will the work be completed?
47.5
49.5
42.5
45.5
- Initially, the total amount of work is calculated as 60 men working for 40 days. So, the work is 60 x 40 = 2400 man-days.
- The first 10 days involve 60 men, so work completed = 60 men x 10 days = 600 man-days.
- 5 men leave after every 10 days, reducing the workforce gradually.
- 10-20 days: 55 men work, so 55 x 10 = 550 man-days completed.
- 20-30 days: 50 men work, so 50 x 10 = 500 man-days completed.
- 30-40 days: 45 men work, so 45 x 10 = 450 man-days completed.
- Remaining work = 2400 - (600 + 550 + 500 + 450) = 300 man-days.
- From day 40 onwards, 40 men work. To complete 300 man-days, it takes 300/40 = 7.5 days.
- Total days = 40 days + 7.5 days = 47.5 days.
The correct option is:
Option 1 — 47.5 days