send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A can do a piece of work in 24 days and B can do it in 80 days. B works alone for 2 days and A works alone on the 3rd day. This process continues till the work is completed. In how many days will the work be completed?
42
45
48
44
- A can complete the work in 24 days. Their work rate is \( \frac{1}{24} \) of the work per day.
- B can complete the work in 80 days. Their work rate is \( \frac{1}{80} \) of the work per day.
- The working pattern follows: B works for 2 days and A works on the 3rd day repeatedly.
- In 2 days, B completes \( \frac{2}{80} = \frac{1}{40} \) of the work.
- On the 3rd day, A completes \( \frac{1}{24} \) of the work.
- Combining their efforts every 3 days: \( \frac{1}{40} + \frac{1}{24} = \frac{3}{120} + \frac{5}{120} = \frac{8}{120} = \frac{1}{15} \).
- In 3 days, they complete \( \frac{1}{15} \) of the work.
- To complete the whole work, 15 cycles of 3 days are needed, totaling 45 days.
So, the correct option is:
Option: 2, 45