send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?
40
43
45
67
Let’s break down the problem:
- Total road to construct: 6 km in 200 days.
- Total people initially: 140.
- Work done in 60 days: 1.5 km.
- Remaining road: 6 - 1.5 = 4.5 km.
- Remaining days: 200 - 60 = 140 days.
- In 60 days, 1.5 km by 140 people, so 1 km by 140 × 60 / 1.5 = 5600 man-days/km.
- So, 4.5 km needs 4.5 × 5600 = 25,200 man-days.
- People required to complete in 140 days: 25,200 / 140 = 180.
- Additional people needed: 180 - 140 = 40.
Explanation of options:
- Option 1: 40 – This is the correct answer.
- Option 2: 43 – Too high, calculation mismatch.
- Option 3: 45 – Slightly higher, again not matching calculated requirement.
- Option 4: 67 – Much too high, not supported by calculations.
Correct Answer: Option 1 (40).