send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A can do a certain work at twice the speed of B. Purther, B can do the same work at 1 5 times the speed of C. All of them together can finish the work in 12 days. In how many days can C alone finish the work ?
45 days
60 days
66 days
- Let C's 1 day's work = x.
- B is 1.5 times as fast as C, so B's 1 day's work = 1.5x.
- A is twice as fast as B, so A's 1 day's work = 2 × 1.5x = 3x.
- Together, in 1 day, they do:
C + B + A = x + 1.5x + 3x = 5.5x
- All together, finish work in 12 days, so daily work = 1/12
- Set up: 5.5x = 1/12 ? x = 1/(12 × 5.5) = 1/66
- So C alone would finish the work in 66 days.
- Option 1: 36 days
- Option 2: 45 days
- Option 3: 60 days
- Option 4: 66 days
By: Parvesh Mehta ProfileResourcesReport error