send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Varun can do a piece of work in 80 days. He works at it for 10 days and then Tarun alone finishes the remaining work in 42 days. The two together could complete the work in :
24 days
25 days
30 days
35 days
Let A = Varun, B = Tarun. Work done by A in 10 days = (1/80) * 10 = 1/8 Remaining work=(1 - (1/8)) = 7/8 Now, 7/8 work is done by B in 42 days Whole work will be done by B in 42 * (8/7) = 48 days. As 1 days work = 1/80 and B's 1 days work = 1/48 (A + B)’s 1 days work = [(1/80) + (1/48)] = 8/240 = 1/30 so, both will finish the work in 30 days.