send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A contract is to be completed in 48 days and 125 men were set to work each working 9 hours a day. After 28 days, 3/7 of the work is completed. How many additional men may be employed, so that the work may be completed in time, each man now working 10 hours day?
80
56
85
42
- Total Work: The contract is to be completed in 48 days with 125 men working 9 hours each day.
- Hence, total work = 125 men × 9 hours/day × 48 days.
- Work Done Till Now: After 28 days, 3/7 of the work is completed.
- So, work left = 4/7 of the total work.
- Current Resources: 125 men, 9 hours/day, for 20 more days.
- Adjustment: Each man will now work 10 hours/day.
- New Condition: To complete the work in the remaining 20 days.
- Calculation: Let's determine additional men.
- New total work by current men = 125 men × 10 hours/day × 20 days.
- Solution: After setting the equation with above details, you need additional men.
- Final Answer: Using the calculation, 85 additional men are needed.
So, the correct option is Option 3: 85.
""