send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Krish can do a piece of work in 4 days, while Rishi can do the same work in 6 days. Both of them work together and get a total
of Rs1,600. What is the share of Rishi?
Rs640
Rs720
Rs580
Rs800
- Krish can complete the entire work in 4 days. Hence, his work rate is 1/4 of the work per day.
- Rishi can complete the entire work in 6 days. So, his work rate is 1/6 of the work per day.
- Working together, their combined work rate is 1/4 + 1/6.
- Simplifying: (3/12) + (2/12) = 5/12 of the work per day is completed together.
- Rishi's share of the work is (1/6) / (5/12) = 2/5.
- Rishi's share of the total payment is (2/5) * Rs1,600 = Rs640.
- Option 1: Rs640 is the correct answer.