send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A and B together can finish a work in 20 days. If they worked together for 8 days, then what was the share of work that was yet
to be completed?
3/5
4/5
2/5
1/5
- A and B can complete the entire work in 20 days when working together.
- In one day, A and B together complete 1/20 of the work.
- They worked together for 8 days. This means they completed 8 * (1/20) = 8/20 = 2/5 of the work.
- The share of the work that remains is the total work minus the completed work.
- Total work = 1 (whole work).
- Completed work = 2/5.
- Remaining work = 1 - 2/5 = 3/5 of the work.
Answer: Option:1 - 3/5
By: santosh ProfileResourcesReport error