send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Sai can do a piece of work alone in 50 days. Ria is 25% more efficient than Sai. What is the number of days that Ria will take to
do the same piece of work alone?
30 days
60 days
40 days
56 days
- Sai can complete the work alone in 50 days.
- Ria is 25% more efficient than Sai. This means Ria can do 125% of the work Sai does in the same time.
- To find how many days Ria takes, we need to determine her efficiency relative to Sai.
- If Sai's work rate is 1/50 of the work per day, Ria's work rate is 1.25 times that.
- Ria's rate = 1.25 x (1/50) = 1/40 of the work per day.
- Therefore, Ria will complete the work in 40 days.
- Correct Answer: Option 3 - 40 days