send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
S1 and S2 can do a piece of work together in 18 days,S2 and S3 can do the same work together in 27 days, while S3 and S1
can do it together in 54 days. In how many days can all 3, working together, do 50% of the work?
8 days
6 days
7 days
9 days
- Let's assume the total work is 1 unit.
- S1 and S2 together can complete 1/18 of the work per day.
- S2 and S3 together can complete 1/27 of the work per day.
- S3 and S1 together can complete 1/54 of the work per day.
- By solving these equations:
- S1 + S2 = 1/18
- S2 + S3 = 1/27
- S3 + S1 = 1/54
- Add all three equations:
- 2(S1 + S2 + S3) = 1/18 + 1/27 + 1/54
- 2(S1 + S2 + S3) = 1/9
- S1 + S2 + S3 = 1/18
- Therefore, all three together can complete 1/18 of the work per day. To complete 50% (0.5) of the work:
- Days = 0.5 / (1/18) = 9 days
- Correct Option: Option 4 - 9 Days
By: santosh ProfileResourcesReport error