send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Ramesh and Ram can do a piece of work in 24 and 30 days respectively. They both started and worked for 6 days. Ram then leaves the work and another their friend Rohit joins the work and completed the remaining work with Ramesh in 11 days . Find how many days are taken by Rohit alone to finish the work?
110 days
132 days
150 days
120 days
Solution: (1/24 + 1/30) *6 +(1/24 + 1/Rohit ) *11 = 1 Therefore ,Rohit takes 120 days to finish the work.