send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A and B can do a piece of work in 24 and 30 days respectively. Both started the work and worked for 6 days. Then B leaves the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C alone can do the work
80
100
120
130
WORK EFFICENCY LCM A = 24 5 120 B = 30 4
B = 6*4 = 24 A = 6*5 = 30 REMAING WORK= 120-54 = 66 A+C = 11 DAYS 66/11 = 6 A EFFICENCY = 5 C EFFICENCY = 1 C WORK = 120 DAY