send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Study the following information and answer the questions that follow: A construction company has completed the construction of a hall of inner dimension 30 m × 20 m × 10 m (L × B × H). The thickness of each of the four wall and the roof is 1 m. Now the work of cementing the floor of the hall and covering the walls inside and outside with tiles is left. Dimension of each tile is 1 m × 1 m. The construction company has 4 workers A, B, C and D for this work of cementing and tiling. Each worker works for 8 hours in a day. And also each worker is specialized in one area which is given in the table below. Worker gets different wage for the work that he is specialized in and the work in which he is not specialized. For each day the wage of the worker is fixed. They are paid this fixed amount even if they do only a fraction of the work that they are supposed to do on that day. The data about Number of tiles that a worker can put in 1 hour and the area that a worker can cement in 1 hour is given in the table below along with their wages. If a worker does both the work of cementing and tiling in the same day, he will be paid the full wage for both the work by the company. Using the above given data answer the questions that follow.
The roof of the hall i.e the top surface area of the hall (outer side) is to be cemented and due to the warm weather outside the efficiency of workers gets halved. B, C and D started to cement the roof. When the work gets completed, B, C and D will get the wage for how many days?
12
13
14
15
With half efficiency B- 1*8= 8 sqm C= 2.5*8=20 sqm D= 2.5*8=20 sqm Total in 1 day=48 sqm total area of roof=32*22=704 sqm total days=704/48=14.66 hence wage for 15 days