send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Sita, Gita and Rita can complete a work in 6, 10 and 15 days resp. Gita and Rita started the work together and worked for ‘x’ days and then both left the work and the remaining work is completed by Sita in 3 days. Find the value of x.
9 days
5 days
8 days
3 days
Total work (LCM of 6,10 and 15) = 30 units Amount of work done by Sita, Gita and Rita in one day resp. = 5, 3 and 2 units Amount of work done by Sita in 3 days = 5*3 = 15 days Amount of work done by Gita and Rita together = 30 – 15 = 15 days Amount of work done by Gita and Rita in one day = 3+2 = 5 days Number of days worked by Gita and Rita together = 15/5 = 3 days