send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Avi and Bindu can complete a project in four and twelve hours, respectively. Avi begins project at 5 a.m., and they work
alternately for one hour each. When will the project be completed?
9 a.m.
11 a.m.
1 p.m.
10 a.m.
- Avi can complete the project in 4 hours, which means he completes 1/4 of the project in one hour.
- Bindu can complete the project in 12 hours, which means she completes 1/12 of the project in one hour.
- They work alternately, starting with Avi. So from 5 a.m. to 6 a.m., Avi works, completing 1/4 of the project.
- From 6 a.m. to 7 a.m., Bindu works, completing 1/12 of the project.
- After 2 hours, they have completed (1/4 + 1/12) = 1/3 of the project.
- They continue this pattern. By 9 a.m., Avi works for 3 hours total, completing 3/4, and Bindu works for 2 hours, completing 1/6.
- By 10 a.m., they would have completed (3/4 + 1/6) = 11/12 of the project.
- Avi works again from 10 to 11 a.m. and completes 1/4 more, finishing the project.
- 11 a.m. is the correct answer.