send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Sanjay can do a piece of work in 50 days. He started the work and left after some days, when 25% work was done. After it Ajit joined and completed it working for 25 days. In how many days Sanjay and Ajit can do the complete work, working together?
6
8
10
20
Explanation : Efficiency of Sanjay = (100/50) = 2% Rest work = 75% Efficiency of Ajit = 75/25 = 3% Combined efficiency of Sanjay and Ajit = 5% Number of days required by Sonu and Abhijeet, to work together = 100/5 = 20 days.