send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Sarthak and Mohan have been assigned a work to design a room for a ceremony, Sarthak can design the entire room in 12 days, while Mohan can design the room in 15 days. In how many days will the work be completed if they work together? (Rounded off to 2 decimal places)
5.67
6.67
1.33
6.00
- Sarthak can complete the room design in 12 days. Therefore, his work rate is 1/12 of the room per day.
- Mohan can complete the room design in 15 days. Thus, his work rate is 1/15 of the room per day.
- If they work together, their combined rate is the sum of their individual rates: (1/12 + 1/15) = (5/60 + 4/60) = 9/60.
- Simplifying 9/60 gives a combined rate of 3/20 of the room per day.
- Hence, working together, they can complete the room design in 20/3 days.
- Simplifying 20/3 gives approximately 6.67 days.
Option:2, 6.67