send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
B is 200% efficient than A and 50% efficient than C, If all of them work together for 2 days to complete the work, then in how many days A alone can complete the work
10 days
12 Days
4 days
6 days
8 days
Let's break down the statements and options:
- B is 200% efficient than A
- This means B is 3 times as efficient as A (A’s efficiency = x, B’s efficiency = x + 200%x = 3x).
- B is 50% efficient than C
- This means B is 1.5 times as efficient as C (C’s efficiency = y, B’s = 1.5y, so y = B/1.5 = 3x/1.5 = 2x).
- Efficiencies:
- A = x
- B = 3x
- C = 2x
- Total = x + 3x + 2x = 6x
- In 2 days, all together do: 2 × 6x = 12x (work done)
- Let total work = W.
- If A alone:
- A in 1 day = x
- W = 12x (from above, as in 2 days all finish it together, so W = 12x)
- So, A needs 12 days to finish it alone.
Relevant calculation for options:
1. 10 days
2. 12 Days
3. 4 days
4. 6 days
5. 8 days
Correct Answer:
Option:2- 12 Days
By: Parvesh Mehta ProfileResourcesReport error