send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A, B and C complete a work in 5 days, 8 days and 12 days, respectively. If they work together and get Rs9.800 for the work, then
how much does A get?
Rs4,600
Rs4,800
Rs4,200
Rs5,800
- A, B, and C work together to complete a task, sharing Rs9,800.
- A completes the work alone in 5 days, B in 8 days, and C in 12 days.
- Calculate each person's contribution per day:
- A's rate: 1/5 of the work per day
- B's rate: 1/8 of the work per day
- C's rate: 1/12 of the work per day
- Together, their combined rate:
- 1/5 + 1/8 + 1/12 = (24/120) + (15/120) + (10/120) = 49/120 of the work per day
- A's share of the total work is (1/5) / (49/120) of the total payment, Rs9,800.
- A's share: Rs9,800 * (24/49) = Rs4,800
- The correct answer is Option:2, Rs4,800.
Report error
Access to prime resources