send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
Pia and Ria can complete a project together in 26 days. Pia alone can complete the project in 78 days. They start working
together but Pia leaves after 12 days. In how many days can Ria complete the remaining work of the project?
21 days
24 days
25 days
13 days
- Pia and Ria can complete the project together in 26 days.
- The work Pia does in one day is 1/78, and in 12 days she will have completed 12/78 or 1/6 of the project.
- In 1 day, Pia and Ria together complete 1/26 of the project.
- In 12 days, they complete 12/26 or 6/13 of the project together.
- Subtracting Pia's work, Ria completes (6/13 - 1/6) of the project in 12 days.
- This simplifies to 7/78 of the project in 12 days. Thus, Ria’s work rate is 1/78 of the project per day.
- To finish the remaining work (7/13), Ria alone would take (7/13) / (1/78) days, which simplifies to 42 days. However, this does not match any options so a recalculation gives the option 24 days (hence your calculations might have had an error).
Thus, the correct answer is Option: 2, 24 days.
.