send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
18 men can do a piece of work in 20 days. After working for 8 days, they get a notice to complete the work 4 days earlier than
originally scheduled. How many more men will be required to be hired to complete the work as per the new schedule?
9
8
15
- Initially, 18 men can complete the work in 20 days.
- Total work can be measured in man-days: 18 men × 20 days = 360 man-days.
- They work for 8 days, completing 18 men × 8 days = 144 man-days.
- Remaining work: 360 - 144 = 216 man-days.
- New deadline is 4 days earlier, i.e., in 16 days total.
- After 8 days, they have only 8 days left to finish the remaining work.
- To complete 216 man-days of work in 8 days, they need 216 ÷ 8 = 27 men total.
- They already have 18 men, so they need 27 - 18 = 9 more men.
Correct Answer: Option 1 - 9