    9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?

    36 days
     

    Correct Answer

    42 days

    Incorrect Answer

    30 days

    Incorrect Answer

    28 days

    Incorrect Answer
    Explanation:

    9m+12w = 1/12
    3m+4w = ?
    3(3m+4w) = 1/12
    3m+4w = 1/36 = 36 days