    10 men can do a work in 25 days. After 12 days of work, 3 more men were engaged to finish the work. The number of days required to complete the remaining work is:

    This questions was previously asked in
    Combined Graduate Level Examination Tier I 2023

    10

    Correct Answer

    8

    Incorrect Answer

    6

    Incorrect Answer

    12

    Incorrect Answer
    Explanation:

    - Total Work Calculation:

    - 10 men can complete the entire work in 25 days.

    - Total work = 10 men × 25 days = 250 man-days.

    - Work Done in First 12 Days:

    - In 12 days, 10 men complete 10 × 12 = 120 man-days of work.

    - Remaining work = 250 - 120 = 130 man-days.

    - Additional Workers:

    - 3 more men join, making it a total of 13 men.

    - Time to Finish Remaining Work:

    - The remaining 130 man-days of work is now being handled by 13 men.

    - Days required = 130 man-days ÷ 13 men = 10 days.

    - ?? Correct Answer: Option:1 - 10

    .