    12 men can complete a painting work in 8 days. However, 16 women can complete the same painting work in 12 days. 8 men started painting the house. After 6 days of painting 2 men were replaced by 4 women. Now how many days will they take to  complete the remaining painting'?

    This questions was previously asked in
    SSC MTS 11th October 2021 Shift-1

    4

    Incorrect Answer

    6

    Correct Answer

    8

    Incorrect Answer

    5

    Incorrect Answer
    Explanation:

    Correct option 2: 6 

    Given 

    12 men can complete a painting work in 8 days.

    So, total work in term of Man's days = 96.

    and One day work of a man = 1/96

    Similarly,

    16 women can complete the same painting work in 12 days.

    One day work of a woman = 1/16x12=1/192

    Now we compare one day work of a man with one day work of a Woman.

    1/96 : 1/192

    1.e. 2:1

    => 1 man = 2 Women.

    Now,  8 men started painting the house. After 6 days of painting 2 men were replaced by 4 women. 

    8 men's 6 days work = 48 units

    Remaining work = 96- 48 = 48 units.

    After 6 days 2 Men replaced with 4 women.  

    Now we have 4 Men + 4 Women

    => 6 Men + 2 Men ( because 4 women are equal to 2 Men)

    => 8 Men

    Now, time required to complete the pending work = .48/8= 6 days