Multiple Choice Questions on 22 boys working together can complete a work in 10 days whereas 25 boys and 12 girls take 8 days to ........... for SSC (MTS) Preparation

Time and work

Quantitative Aptitude (MTS)

Title

45:30

Video Progress

8 of 24 completed

Notes Progress

5 of 15 completed

MCQs Progress

38 of 100 completed

Subjective Progress

8 of 20 completed

Continue to Next Topic

Indian Economy - Understanding the basics of Indian economic system

Next Topic

    22 boys, working together, can complete a work in 10 days, whereas 25 boys and 12 girls take 8 days to complete the same

    work In how many days can only 6 girls, working together, complete the same work?

    This questions was previously asked in
    SSC MTS 25th July 2022 Shift-1

    170

    Incorrect Answer

    177

    Incorrect Answer

    175

    Incorrect Answer

    176

    Correct Answer
    Explanation:

    - Work Rate of Boys: 22 boys can complete the work in 10 days. So, the work done by one boy in one day is 1/220 work unit.

    - Combined Rate of Boys and Girls: 25 boys and 12 girls complete the work in 8 days.

    - Equation Setup:

    - Work by 25 boys in one day = 25/220 work units.

    - Combined work by 25 boys and 12 girls in one day = 1/8 work unit.

    - Therefore, work by 12 girls = (1/8) - (25/220).

    - Simplifying the equation: 12 girls do (55/440 - 25/220) = 1/16.8 work units per day.

    - Solution for 6 Girls:

    - Since 12 girls complete 1/16.8 work per day, 6 girls will do half: 1/33.6 work units per day.

    - Days needed = Reciprocal of 1/33.6 = 33.6 * 10 (to match boy's equation setup) = 336

    - Divide by 2 because each girl is half productivity of the joint rate needs to finish. days required = 176.

    - Final Answer and Option:

    - 6 girls complete the work in 176 days.

    - Option 4: 176 is correct.