    16 men can paint 15 walls in 45 days. In how many days can 20 men paint 20 walls?

    This questions was previously asked in
    SSC CHSL 25th May 2022 Shift-2

    40

    Incorrect Answer

    60

    Incorrect Answer

    48

    Correct Answer

    45

    Incorrect Answer
    Explanation:

    - First, calculate the work rate for 16 men painting 15 walls in 45 days.

    - Total work = 15 walls; Total man-days = 16 men × 45 days = 720 man-days.

    - Work rate = 720 man-days / 15 walls = 48 man-days per wall.

    - Now, find out the time taken by 20 men to paint 20 walls.

    - Total work for 20 walls = 20 walls × 48 man-days/wall = 960 man-days.

    - Days required = Total man-days / Number of men = 960 man-days / 20 men = 48 days.

    - Option 3: 48 is the correct answer.