send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A and B together can finish a work in 30 days. They worked for it for 20 days and then B left the work. The remaining work was done by A alone in 20 days more. In how many days can A alone finish the work?
48 days
50 days
54 days
60 days
(A + B)’s combined efficiency = 100/30 = (10/3)%. The work done by both in 20 days= 20*(10/3) = (200/3)%. Remaining work = 100 – (200/3) = (100/3)%. If A does (100/3)% of work in 20 days, then A’s one day work = (100/60)%. Hence, A will alone finish the work in = 100/(100/60) = 60 days.
By: MIRZA SADDAM HUSSAIN ProfileResourcesReport error