send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
If 18 men can cut a field in 35 days, then in how many days can 21 men cut the samefield?
27
28
30
32
- When 18 men can complete the task in 35 days, the total man-days required are 18 men * 35 days = 630 man-days.
- The work remains constant, so 21 men will still require 630 man-days to cut the field.
- To find the number of days required for 21 men, divide the total man-days by the number of men: 630 man-days / 21 men = 30 days.
- Therefore, 21 men can cut the field in 30 days.
- Option 1: 27 days - Incorrect as it’s less than the calculated days.
- Option 2: 28 days - Incorrect as it’s less than the required days.
- Option 3: 30 days - Correct, matches the calculated days.
- Option 4: 32 days - Incorrect as it’s more than needed.