send mail to support@abhimanu.com mentioning your email id and mobileno registered with us! if details not recieved
Resend Opt after 60 Sec.
By Loging in you agree to Terms of Services and Privacy Policy
Claim your free MCQ
Please specify
Sorry for the inconvenience but we’re performing some maintenance at the moment. Website can be slow during this phase..
Please verify your mobile number
Login not allowed, Please logout from existing browser
Please update your name
Subscribe to Notifications
Stay updated with the latest Current affairs and other important updates regarding video Lectures, Test Schedules, live sessions etc..
Your Free user account at abhipedia has been created.
Remember, success is a journey, not a destination. Stay motivated and keep moving forward!
Refer & Earn
Enquire Now
My Abhipedia Earning
Kindly Login to view your earning
Support
Type your modal answer and submitt for approval
A can do a piece of wrk in 120 day and B can do it in 150 days. They work tgether for 20 day. Then B leaves and A alone cntinues the work. After 12 days C joins A and the work is cmpleted in 48 day more. In how many days can C do it if he works alne?
130 days
150 days
240 days
260 days
In one day, work done by A = 1/120 In one day, work done by B = 1/150 So, work A and B together can complete in a day= 1/120+1/150=3/200 In 20 days = 3/200∗20=3/10 Work done by A in 12 Days = 12∗1/120=1/10 Let us assume C alone can finish the work in x days In one day, work done by C = 1/x Now, 48∗(1/120+1/x)+3/10+1/10=1 x=240 So, C alone could finish the job in 240 days.